Alyeska Strategic Reconfiguration Project
AES Power, Pipeline, and Communications is providing services for the Trans Alaska Pipeline System as part of the strategic reconfiguration of pump stations 4 and 9. The project began in 2005 and is currently being executed on a fast-track basis. Total construction manhours are expected to exceed 800,000 when the project is completed in July 2007.
The project objectives include:
- Minimizing the cost of transportation and extending the economic life of the Trans Alaska Pipeline System and North Slope oil fields
- Constructing modular and scalable facilities to accommodate throughput variations more efficiently
- Simplifying facilities, renewing assets, and automating using proven technology
- Maintaining reliability, safety, and operational integrity
|
We are providing the following services:
- Module fabrication
- Constructability reviews
- Construction planning
- Work package development
- CPM schedule development and maintenance
- Earned value project management and controls system
- Pile foundation installations
- Heavy rigging and lifts
- Turbine generator installation
- Electrical, controls, and pump, and piperack module installation
- Facility piping, electrical, and controls systems interconnects
- Construction completion testing
- Functional checkout and startup assistance
|
|
|