Alpine 2005 On-Pad Installation Project
The scope of work included installation of ACX2 trim coolers; a tank skid and corrosion inhibitor tank; piperacks and tie-ins for CD3, CD4, ACX3, and a road crossing for CD3. We erected a fleet maintenance building, installing underground piping and electrical, thermal siphons, civil package, structural steel, architectural, electrical and instrumentation, piping, and HVAC. We also completed the underground civil and piping for the CD3 road crossing. We met our schedule milestones, including mobilizing during the last week of March, and completing the heavy lifts by mid-April; this enabled a timely demobilization of a 300-ton crane prior to the closure of the ice road. We provided the following services:
|